A plant has two categories of overhead: maintenance and inspection. Costs expect
ID: 2514550 • Letter: A
Question
A plant has two categories of overhead: maintenance and inspection.
Costs expected for these categories for the coming year are as follows:
Machine maintenance $120,000
Inspection $200,000
Total expected overhead: $320,000 (120,000 + 200,000 from above)
Expected activity levels for the coming year are as follows:
80,000 direct labor hours
40,000 machine hours
2,500 inspections
The following data has been assembled for use in developing a bid for a proposed job:
What would be the total cost of the potential using the activity-based costing and the appropriate cost drivers?
Direct materials $1,500 Direct labor $5,000 Machine hours 400 Number of inspections 6 Direct labor hours 750Explanation / Answer
Total cost of the potential using the activity-based costing and the appropriate cost drivers is $8,180
Direct materials $1,500
Direct labour $5,000
Overhead:
($1,20,000/40,000) x 400 $1,200
($2,00,000/2500) x 6 $480
Total cost $8,180