Continuous Flow vs. Departmental Flow Manufacturing Anderson Company has the fol
ID: 2522847 • Letter: C
Question
Continuous Flow vs. Departmental Flow Manufacturing
Anderson Company has the following departmental manufacturing structure for one of its products:
3. What if the processing times of molding, welding, and assembly are all reduced to six minutes each? What is the production rate now?
units per hour
How long will it take to produce a batch of 20 units?
minutes
Explanation / Answer
If the production time of molding, welding, and assembly are reduced to 6 minutes each and polishing time is 12 min then per unit processing time = 3*6min + 12 min =30 min
Units per hour = 60/30 min = 2 units per hour
Time required to produce 20 units = 20units * 30 min
=600 min i.e., 600/60 = 10 hrs