Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Use the following for the next five questions: The following data is given for t

ID: 2577159 • Letter: U

Question

Use the following for the next five questions: The following data is given for the Walker Company: Budgeted production...............................................1,000 units Actual production........................................................980 units Materials: Standard price per lb..................................................... ..$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.............11,800 Actual price paid for materials........................................$23,000 Labor: Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928 The direct material price variance is: $600 F $600 U $80 F $80 U

Explanation / Answer

Formula: Direct material Price Variance = (Actual Price - Budgeted price)*Actual Quantity

= ($23,000 - $2*11,800)

Hence the option is A ie., 600F

Direct material price variance is 600F

Formula: Direct material Price Variance = (Actual Price - Budgeted price)*Actual Quantity

= ($23,000 - $2*11,800)

= ($23,000 - $23,600) = 600 F

Hence the option is A ie., 600F

Direct material price variance is 600F

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote