Nelson Extruding produces containers for nurseries and landscaping businesses. T
ID: 2595149 • Letter: N
Question
Nelson Extruding produces containers for nurseries and landscaping businesses. The company competes based on its low-cost, high-quality products. As the company’s expenses have risen, management has become concerned with the need to streamline various processes in order to reduce costs without reducing quality. The following table shows the time needed to produce a batch of 1-inch plant flats:
Explanation / Answer
(a)
Manufacturing cycle time = Process time + Inspection time + Move time + Queue time
= 32 minutes + 43 minutes + 3 minutes + 3 minutes + 8 minutes
= 89 minutes
(b)
Value-added time = Process time = Production in station 1 + Production in station 2
= 32 minutes + 43 minutes = 75 minutes.