Compar y?sconsidering two mutually exclusive pro ects The tm which has a cost of
ID: 2620219 • Letter: C
Question
Compar y?sconsidering two mutually exclusive pro ects The tm which has a cost of capital of 10%, has estnated its cash nows as sho ninthe fol mg tabl Calculate the NPV of each project, and assess ts acceptabity b. Calculate the IRR for each project, and assess its acceptability a. The NPV of project Aiss( Round to the nearest cent) According to the NPV method, is project A acceptable? (Select the best answer below) Data Table (Click on the icon located on the top-right corner of the data table below in order to copy its contents into a spreadsheet.) No O Yes The NPV of project B is s (Round to the nearest cent.) Is project B acceptable on the basis of NPV? (Select the best answer below) O Yes O No b. The iRR of project Ais?%, (Round to two dec mal places ) is project A acceptable on the basis of IRR? (Selegt the best answer below) Project 8 s 99,000 Initial investment $110,000 CFo) 0 Cash infnlowS (CF. Year (o $35,000 $40,000 $40,000 540,000 520,000 25.000 520 000 Print Done No ?Yes The IRR of project B is?% (Round to two decimal places ) Click to select your answersExplanation / Answer
Project A
Year
cash flow
present value of cash flow = cash flow/(1+r)^n r= 10%
0
-110000
-110000
1
25000
22727.27
2
35000
28925.62
3
40000
30052.59
4
40000
27320.54
5
50000
31046.07
NPV
sum of present value of cash flow
30072.09
Yes it is accepted
Project B
Year
cash flow
present value of cash flow = cash flow/(1+r)^n r= 10%
0
-99000
-99000
1
50000
45454.55
2
40000
33057.85
3
20000
15026.3
4
25000
17075.34
5
20000
12418.43
NPV
sum of present value of cash flow
24032.46
Yes it is accepted
Project A
Year
cash flow
0
-110000
1
25000
2
35000
3
40000
4
40000
5
50000
IRR = Using IRR function In MS excel =irr(-110000,25000,35000,40000,40000,50000)
19.13%
Yes it is accepted
Project B
Year
cash flow
0
-99000
1
50000
2
40000
3
20000
4
25000
5
20000
IRR = Using IRR function In MS excel =irr(-99000,50000,40000,20000,25000,20000)
21.17%
Yes it is accepted
Project A
Year
cash flow
present value of cash flow = cash flow/(1+r)^n r= 10%
0
-110000
-110000
1
25000
22727.27
2
35000
28925.62
3
40000
30052.59
4
40000
27320.54
5
50000
31046.07
NPV
sum of present value of cash flow
30072.09
Yes it is accepted
Project B
Year
cash flow
present value of cash flow = cash flow/(1+r)^n r= 10%
0
-99000
-99000
1
50000
45454.55
2
40000
33057.85
3
20000
15026.3
4
25000
17075.34
5
20000
12418.43
NPV
sum of present value of cash flow
24032.46
Yes it is accepted
Project A
Year
cash flow
0
-110000
1
25000
2
35000
3
40000
4
40000
5
50000
IRR = Using IRR function In MS excel =irr(-110000,25000,35000,40000,40000,50000)
19.13%
Yes it is accepted
Project B
Year
cash flow
0
-99000
1
50000
2
40000
3
20000
4
25000
5
20000
IRR = Using IRR function In MS excel =irr(-99000,50000,40000,20000,25000,20000)
21.17%
Yes it is accepted
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.