What is the IRR for each of these projects? ( Do not round intermediate calculat
ID: 2628618 • Letter: W
Question
What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answer as a percentage roundedto 2 decimal places (e.g., 32.16).)
Assume the required return is 11 percent. What is the NPV for each of these projects? (Do not round intermediate calculations.Round your answers to 2 decimal places (e.g., 32.16).)
Over what range of discount rates would you choose Project A? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)
Over what range of discount rates would you choose Project B? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)
At what discount rate would you be indifferent between these two projects? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)
Romboski, LLC, has identified the following two mutually exclusive projects:Explanation / Answer
1 Project A 22.83 IRR NPV at 11% discount rate 11,679.44
Project B 21.16 IRR NPV at 11% discount rate 12,848.21
With IRR you select A, with NPV you select B
You would select A at discount rates above 21,16 and B at discount rates below. 21,16 is where you are indifferent.