A project that provides annual cash flows of $16,800 for nine years costs $74,00
ID: 2642125 • Letter: A
Question
A project that provides annual cash flows of $16,800 for nine years costs $74,000 today.
What is the NPV for the project if the required return is 8 percent? (Round your answer to 2 decimal places. (e.g., 32.16))
At a required return of 8 percent, should the firm accept this project?
What is the NPV for the project if the required return is 20 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16))
At a required return of 20 percent, should the firm accept this project?
At what discount rate would you be indifferent between accepting the project and rejecting it? (Round your answer to 2 decimal places. (e.g., 32.16))
A project that provides annual cash flows of $16,800 for nine years costs $74,000 today.
Explanation / Answer
NPV = CF0 + A * (1-(1+i)^-n)/i
a) NPV at 8% = -74000 + 16800 * (1-(1+.08)^-9)/.08 = 30948
b) Yes, project should be accepted as it has positive NPV.
c) NPV at 20% = -74000 + 16800 * (1-(1+.20)^-9)/.20 = (-) 6280
d) No, project should not be accepted as it has negative NPV.
e) Indifferent rate: -74000 + 16800 * (1-(1+i)^-9)/i = 0
i = 17.30%
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.