Find the discounted Payback period for the following project. The discount rate
ID: 2654314 • Letter: F
Question
Find the discounted Payback period for the following project. The discount rate is 9% Project X Initial outlay $ 8,644.00 Year 1 $ 3,099.00 Year2 $ 3,942.00 Year 3 $ 5,447.00 Year 4 $ 7,880.00 Round the answer two decimal places Find the discounted Payback period for the following project. The discount rate is 9% Project X Initial outlay $ 8,644.00 Year 1 $ 3,099.00 Year2 $ 3,942.00 Year 3 $ 5,447.00 Year 4 $ 7,880.00 Round the answer two decimal placesExplanation / Answer
Discounted Payback period = 2 + 2482.98/4206.08
Discounted Payback period = 2.59 Years
Working
Project X Cash flow PV Factor @ 9% Present Value Cumulative of PV of Cash flow [a] [b] [c = a*b] [ d = previous d + c] Initial outlay -8644 1.00000 -8644 -8644 Year 1 3099 0.91743 2,843.12 -5800.88 Year2 3942 0.84168 3,317.90 -2482.98 Year 3 5447 0.77218 4,206.08 1,723.11 Year 4 7880 0.70843 5,582.39 7,305.50Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.