You are analyzing a project and have prepared the following data: Year Cash Flow
ID: 2700012 • Letter: Y
Question
You are analyzing a project and have prepared the following data:
Year Cash Flow
0 -$ 169,000
1 $ 46,200
2 $ 87,300
3 $ 41,000
4 $ 39,000
Required Payback period is 2.5 Years
Required Return 8.50%
1. What is the profitability index for this project? Should you accept the project?
2. What is the Internal Rate of Return for this project? Should you accept or reject the project?
3. What is the Net Present Value for this project? Should you accept or reject the project?
4. What is the Payback Period for this project? Should you accept or reject the project?
PLEASE SHOW ALL WORK!!!!
Explanation / Answer
1. PV Index is ratio of the present value of Futuer CFs to Initial investment
So PV of CFs = 46200/(1+8.5%)^1 + 87300/(1+8.5%)^2+41000/(1+8.5%)^3 + 39000/(1+8.5%)^4 = $176,978.72
SO PI Index = $176,978.72/169000 = 1.05
2. IRR = IRR(CF0..CF4)
= IRR(-169000,46200,87300,41000,39000)
= 10.75%
As IRR is more than Reqd return 8.5%, Project should be accepted.
3. NPV = PV of CFs + CF0 = $176,978.72 - 169,000 = $7,978.72
As NPV is Positive, Project should be accepted
4. Paypabck period:Cash PBP = Payback period (PBP) = Year before full recovery + (Unrecovered cost at start of year/Cash flow during year)
We see that CFs in 2 yrs =46200+87300 =133500
CF in Y3 = 41000. But Cumuulative CFs from Y1 to Y3 is more than Initial Inv. So our PBP is between 2 & 3 yrs.
SO PBP = 2 + (169000-133500)/41000 = 2.87 years
As PBP is more than Reqd PBP of 2.5Yrs, We shouldn't accept project
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.