Compute the NPV statistic for Project Y and tell [advise] whether the firm shoul
ID: 2703485 • Letter: C
Question
Compute the NPV statistic for Project Y and tell [advise] whether the firm should accept or reject the project with the cash flows shown in the chart if the appropriate cost of capital is 12 percent.
Project Y
Time
0
1
2
3
4
Cash Flow
-$11,000
$3,350
$4,180
$1,520
$2,000
(Cornett, Adair, & Nofsinger, 2014).
Time
0
1
2
3
4
Cash Flow
-$11,000
$3,350
$4,180
$1,520
$2,000
Compute the NPV statistic for Project Y and tell [advise] whether the firm should accept or reject the project with the cash flows shown in the chart if the appropriate cost of capital is 12 percent. Project YExplanation / Answer
Hi,
Please find the answer as follows:
NPV = -11000 + 3350/(1+.12)^1 + 4180/(1+.12)^2 + 1520/(1+.12)^3 + 2000/(1+.12)^4 = -2323.72 or -2324
The project should not be accepted as NPV is negative.
Thanks.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.