Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Compute the NPV of the following project using discount rates of 10% and 20% P r

ID: 2717645 • Letter: C

Question

Compute the NPV of the following project using discount rates of 10% and 20%

              Project A:     C0                            C1                                    C2                        

                                 –7,500              5000                      5000

Thompson Industries has a project with the following projected cash flows:

Cash flow year 0: ($240,000)

Cash flow year 1: $25,000

Cash flow year 2: $75,000

Cash flow year 3: $150,000

Cash flow year 4: $150,000

             Using a 10% discount rate for this project, what is the NPV of this project? Should the

             project be accepted or rejected?

Your required rate of return is 8%. If you invest $15,000 today in a project, you will receive the following cash flows:

At the end of Year 1 $7000

At the end of Year 2 $8000

At the end of Year 3 $9000

What is the NPV of the project? What is the payback period of the project?

How to compute a project’s IRR?

Explanation / Answer

NPV at 10%

Year

Cash Flow

PV factor 10%

PV

0

-7500

1.0000

-7500.00

1

5000

0.9091

4545.45

2

5000

0.8264

4132.23

NPV

1177.69

NPV at 20%

Year

Cash Flow

PV factor 20%

PV

0

-7500

1.0000

-7500.00

1

5000

0.8333

4166.67

2

5000

0.6944

3472.22

NPV

138.89

Hence, At 10% discount rate, NPV is 1177.69 and at 20% discount rate NPV is 138.89.

Year

Cash Flow

PV factor 10%

PV

0

-7500

1.0000

-7500.00

1

5000

0.9091

4545.45

2

5000

0.8264

4132.23

NPV

1177.69

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote