Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The Trektronics store begins each week with 500 phasers in stock. This stock is

ID: 2717684 • Letter: T

Question

The Trektronics store begins each week with 500 phasers in stock. This stock is depleted each week and reordered. The carrying cost per phaser is $45 per year and the fixed order cost is $90.

  

  

   

  

What is the economic order quantity? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

    

The Trektronics store begins each week with 500 phasers in stock. This stock is depleted each week and reordered. The carrying cost per phaser is $45 per year and the fixed order cost is $90.

Explanation / Answer

(a) Computation of the current total carrying costs.We have,

Total carrying cost = Number of inventory x Carrying cost per unit per year

Total Carrying cost = 500 x 45.00 = $ 22,500.00

(b) Computation of  the current restocking costs.We have,

Restocking costs = Number of order x per order cost

Restocking costs = 52 x $ 90.00 = $ 4,680.00

(c) Computation of the economic order quantity(EOQ).We have,

EOQ = [ 2 X Annual consumption x Buying cost per order / Cost of carrying one unit of inventory for one year]1/2

EOQ = [ 2 X (500 X 52) X 90 / 45 ]1/2 = 322 units

EOQ = 322 units

(d) Trektronics should decrease 178 units ( 500 - 322) its order size.

(e) Order per year = Annual Demand / EOQ

Order per year = 26,000 / 322 = 80.75

Hence, order per year is 80.75 place under the new policy.