Compute the discounted payback statistic for Project C if the appropriate cost o
ID: 2745516 • Letter: C
Question
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 9 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Should the project be accepted or rejected?
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 9 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Explanation / Answer
Cash flow PV cumulative at the end of 1 year=-1500+680/1.09^1=-876.15
Cash flow PV cumulative at the end of 2 year=-1500+680/1.09^1+630/1.09^2=-345.89
Cash flow PV cumulative at the end of 3 year=-1500+680/1.09^1+630/1.09^2+670/1.09^3=171.47
Cash flow PV of year 3 cash flows=670/1.09^3=517.36
DPB=2+345.89/517.36=2.67 YEARS
ACCEPT AS IT IS LESS THAN 3 YEAR
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.