I need help in Earn value The following eight activities constitute an overall b
ID: 2777072 • Letter: I
Question
I need help in Earn value
The following eight activities constitute an overall bar chart portrayal of a 6-month project. Three months after the start of construction. Activities A, B, C, D, half of E, and one-fourth of F were completed, for a cost of $20,500. Evaluate the status of the project. Using earned value concepts, determine the schedule variance and the cost variance, the percentage completion, and EAC. State if the project is over or under budget and if it is ahead of or behind schedule. Show detail calculations of all earn value cost parameters.Explanation / Answer
After 3 months, Actual Cost (AC) = 20,500
Budget of Completion (BAC) = 40,000
Earned Value (EV) = A + B + C + D + 50% of E + 25% of F = (2000+ 8000+2000+1000+8000/2+15000/4) = 20,750
Planned Value (PV) = A + B + C + D + 50% of E + 33.3% of F = (2000+ 8000+2000+1000+8000/2+15000/3) = 22000
Now,
Cost Variance = Earned Value – Actual Cost
CV = EV – AC = 20750 – 20,500 = 250
Schedule Variance = Earned Value – Planned Value = 20750 - 22000 = -1,250
Percentage completion = EV / BAC = 20750 / 40000 = 51.87%
Cost Performance Index (CPI) = EV / AC = 20750 / 20500 = 1.01
Estimate at Completion (EAC) = BAC/CPI = 40000 / 1.01 = $ 39,603.96
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.