Given is a PERT project network diagram as shown below. Activity Start A B C D E
ID: 3134305 • Letter: G
Question
Given is a PERT project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
Time
0
3.16
2.23
7.29
3.16
1.89
2.63
5.42
3.59
0
a) The Project Completion time = Blank 1(in 2 decimal places)
b) The Earliest Start time, ES, of Activity G = Blank 2(in 2 decimal places)
c) The Latest Finish time, LF, of Acitivity C = Blank 3(in 2 decimal places)
d) The critical activities are = Blank 4(ex. type in critical activities as ABCD, no comma, no space)
Activity
Start
A
B
C
D
E
F
G
H
End
Time
0
3.16
2.23
7.29
3.16
1.89
2.63
5.42
3.59
0
Explanation / Answer
a)
project completion = 29.37
b) earliest start time of G is 5.42
c) thelatest finis time of C = 12.68
d) critical activities are = A and G
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.