Given is a PERT project network diagram as shown below. Activity Start A B C D E

ID: 3134305 • Letter: G

Question

Given is a PERT project network diagram as shown below.

Activity

Start

A

B

C

D

E

F

G

H

End

Time

0

3.16

2.23

7.29

3.16

1.89

2.63

5.42

3.59

0


a) The Project Completion time = Blank 1(in 2 decimal places)

b) The Earliest Start time, ES, of Activity G = Blank 2(in 2 decimal places)

c) The Latest Finish time, LF, of Acitivity C = Blank 3(in 2 decimal places)

d) The critical activities are = Blank 4(ex. type in critical activities as ABCD, no comma, no space)

Activity

Start

A

B

C

D

E

F

G

H

End

Time

0

3.16

2.23

7.29

3.16

1.89

2.63

5.42

3.59

0

Explanation / Answer

a)

project completion = 29.37

b) earliest start time of G is 5.42

c) thelatest finis time of C = 12.68

d) critical activities are = A and G