Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Given is a Project with network diagram and activity times as shown below. Activ

ID: 3177101 • Letter: G

Question

Given is a Project with network diagram and activity times as shown below.

Activity

        A              

B

       C    

       D

       E

     F

      G

    H             

I                  

J   

Time (wks)

       11

8

      11

      15

      13

     19

      15    

      9

16

11



a) The Earliest Start (ES) time of Activity I = __________ weeks

b) The Latest Start (LS) time of Activity B = __________weeks

c) The Slack time of Activity C = __________weeks

d) The Earliest Finish (EF) time of Activity H = _________weeks

e) The Latest Finish (LF) time of Activity B = __________weeks

f) The Project Completion time = ___________weeks

Activity

        A              

B

       C    

       D

       E

     F

      G

    H             

I                  

J   

Time (wks)

       11

8

      11

      15

      13

     19

      15    

      9

16

11

Given is a Project with network diagram and activity times as shown below. Start 11 13 19 ctivity

Explanation / Answer

The different paths of the project are as follows:

1.Start-->A-->B-->E-->H-->J = 11 + 8 + 13 + 9+11 = 52 weeks

2.Start-->A-->B-->G-->I-->J = 11+8+15+16+11 = 61 weeks

3.Start-->A-->C-->H-->J = 11+11+9+11 = 42 weeks

4.Start-->D-->F-->I-->J = 15+19+16+11 = 61 weeks

2 and 4 are critical paths of the project

a) I cannot be started unless G and F are done,

Early finish of F = 15 + 19 = 34

Early finish of G = 11+8+15 = 34

Since both are 34, the Early start of Activity I is 34 weeks

b) Latest time of activity B , Since B is in the critical path

The Latest time of activity B is same as early start = 11 weeks

c) The Slack time of Activity C,

Slack time = Late start - Early start of activity C = 21 - 11 = 10 weeks

Late start is the longer path time of activity H - Activity C time = 32 - 11 = 21

The Slack time of Activity C = 10 weeks

d) The Earliest Finish (EF) time of Activity H = 32 + 9 = 41 weeks

e) Latest Finish time of activity B = Late start + activity B time = 11+8 = 19 weeks

f) The project completion time is the time of the critical path = 61 weeks

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote