Can I got the answers for this 4 Problems Four problems, 25 pts each. Each probl
ID: 3209686 • Letter: C
Question
Can I got the answers for this 4 Problems Four problems, 25 pts each. Each problem will be graded as follows: Correct final answer/conclusion: Correct problem formulation with cash flow tablediagram 25% Correct economic equations and solutions leading to the final answer 25% 50% * Problem1. A new alloy can be produced by Process A, which costs $200,000 to implement. The operating cost will be 10,000 per quarter with a salvage value of S25,000 after its 2-year life. Process B will have a first cost of $250,000, an operating cost of S 15,000 per quarter, and a S40.000 salvage value after its 4-year life. The interest rate is 8% per year compounded quarterly. What is the present value difference between A and B? (10 pts) ANALYSIS:Explanation / Answer
For present worth method, both alternatives must have equal lives of 16 quarters (4-year life).Useidentical equipment replacement for process A at the end of 8th quarter (2-year) at 2% per quarter:
Present worth of process A:
PWA= -$200,000 - $200,000(P/F, 2%, 8) - $10,000(P/A, 2%, 16)+ $25,000(P/F, 2%, 8) + $25,000(P/F. 2%, 16)
= -$200,000(1 +.8535) - $10,000(13.578) + $25,000(1 + .7284)
= -$466,933
Present worth of process B:
PWB= -$250,000 - $15,000(P/A, 2%, 16) + $40,000(P/F. 2%, 16)
= -$250,000 - $15,000(13.578) + 40,000(.7284)
= -$424,534
PW of cost of process B is less than PW of cost of process A
sorry for the inconvenience but according to chegg policy i can give answer for the first question only.
i hope you can understand the above concept.
but if still you have doubt then you can ask me in the comment section.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.