Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

In the following table the activities with their precedence sequence and expecte

ID: 333027 • Letter: I

Question

In the following table the activities with their precedence sequence and expected time? (days) are listed for a project on which Carl? Betterton's construction company is? working:

In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working Activity Immediate Predecessor(s) Time (days) 4 6 E, F Carl's team should be able to complete the project in days Critical path activities for Carl's project are A-C-F-H A-B-E-H A-B-D-G

Explanation / Answer

a) Length of project = 41 days  

b) Critical Path= ABEH = 3 + 4 + 4 + 8= 19

StartA (3) B (4) C (6) D (6) F(4) E (4) G (6)

H (8)

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote