Calibri Copy Formatting" Paste Format Painter Number Alignment Font Clipboard A4 | P301-Problem 10 The Internet Retail distributor from problem 9 has also decided to use the ROP system for determining when to place an order. The purchasing manager has determined that the monthly demand for crates of 24000 has a standard deviation of 2500. The current supplier of the boxes has a .5 month lead time. 3 1. If the manager wants a 90% customer service level on the crates, what should the ROP be for this item? 2. If the manager were to switch to a 95% customer service level how much more safety stock would be needed? 5 6 10 HW Problem 10Explanation / Answer
1. Reorder point formula is:
R = D*L + Z*SD*(L)1/2
where R is reorder point,
D is average monthly demand,
L is the lead time
Z is the number of standard deviations corresponding to service level
SD is the standard deviation
For 90% service level, Z value is 1.645
So R = 24000*0.5 + 1.645*2500*(0.5)1/2
= 12000 + 2907.98
= 14907.98 = 14908
So reorder point for 90% customer service level is 14908 crates.
2. Safety stock is as calculated below:
SS = Z*SD*(L)1/2
where SS is the Safety Stock
Z is the number of standard deviations corresponding to service level
SD is the standard deviation
L is the lead time
Z value for 95% service level is 1.96
So SS = 1.96*2500*(0.5)1/2
= 3464.82 = 3465
So safety stock for 95% customer service level is 3465 stock.