Create a first draft of a WBS from the scenario below. Makeassumptions as needed
ID: 3609072 • Letter: C
Question
Create a first draft of a WBS from the scenario below. Makeassumptions as needed based on the section about project planningconsiderations and constraints in the chapter. In your WBS,describe the skill sets required for the tasks you have planned.Scenario
Sequential Label and Supply is having a problem with employeessurfing the Web to access material the company has deemedinappropriate for use in a professional environment. The technologyexists to insert a filtering device in the company Internetconnection that blocks certain Web locations and certain Webcontent. The vendor has provided you with some initial informationabout the filter. The hardware is an appliance that costs $18,000and requires a total of 150 effort-hours to install and configure.Technical support on the appliance costs 18 percent of the purchaseprice and includes a training allowance for the year. A softwarecomponent is needed for administering the appliance that runs onthe administrator’s desktop computer and it costs $550. Amonthly subscription provides the list of sites to be blocked andcosts $250 per month. The administrator must spend an estimatedfour hours per week for ongoing administrative functions.
Items you should consider:
· Yourplan requires two sections, one for deployment and another forongoing operation after implementation.
· Thevendor offers a contracting service for installation at $140 perhour.
· Yourchange control process requires a 17-day lead time for changerequests.
· Themanufacturer has a 14-day order time and a 7-day delivery time forthis device.
Explanation / Answer
Draft Sample Implementation WBS:
Item
TASK
Resources
Start & End Dates
Effort Hours
Capital
Expense
Non-Capital
Expense
Dep.
1
Contact Network team to ensure hardware device will work withnetwork infrastructure
Network Engineers
S: 11/25 E:11/27
2
$0
$100
2
Purchase Web Filter
Network Engineer & Purchasing Group
S:11/28 E:12/19
1
$18,000
$0
1
3
Purchase Technical Support Contract
Purchasing Group
S:11/28 E:12/19
1
$3,240
$0
1
4
Purchase additional software components
Purchasing Group
S:11/28 E:12/19
1
$800
$0
1
5
Submit change request to implement hardware
Change control board
S:12/19 E:01/06
1
$0
$0
2
6
Send administrator to training on device
Training center and Administrator
S:01/06 E:01/10
40
$0
$0
3
7
Install hardware and software components.
Outside vendors
S:01/06 E:01/20
150
$0
$21,000
2,4
Item
TASK
Resources
Start & End Dates
Effort Hours
Capital
Expense
Non-Capital
Expense
Dep.
1
Ongoing administration of device
Administrator
Ongoing
4/WK
$0
$0
2
Monthly subscription
Administrator/Purchasing Group
Ongoing
250/Month
$0
Item
TASK
Resources
Start & End Dates
Effort Hours
Capital
Expense
Non-Capital
Expense
Dep.
1
Contact Network team to ensure hardware device will work withnetwork infrastructure
Network Engineers
S: 11/25 E:11/27
2
$0
$100
2
Purchase Web Filter
Network Engineer & Purchasing Group
S:11/28 E:12/19
1
$18,000
$0
1
3
Purchase Technical Support Contract
Purchasing Group
S:11/28 E:12/19
1
$3,240
$0
1
4
Purchase additional software components
Purchasing Group
S:11/28 E:12/19
1
$800
$0
1
5
Submit change request to implement hardware
Change control board
S:12/19 E:01/06
1
$0
$0
2
6
Send administrator to training on device
Training center and Administrator
S:01/06 E:01/10
40
$0
$0
3
7
Install hardware and software components.
Outside vendors
S:01/06 E:01/20
150
$0
$21,000
2,4