Manceville Air has just produced the first unit of a large industrial compressor
ID: 361871 • Letter: M
Question
Manceville Air has just produced the first unit of a large industrial compressor that incorporated new technology in the control circuits and a new internal venting system. The first unit took 112 hours of labor to manufacture. The company knows from past experience that this labor content will decrease significantly as more units are produced. In reviewing past pro- duction data, it appears that the company has experienced a 90% learning curve when producing similar designs. The company is interested in estimating the total time to complete the next 7 units. Your job as the production cost estimator is to prepare
Explanation / Answer
We have to find out total time to complete next 7 units , which will be = Total time to complete first 8 units – time to complete first unit
Given are following data :
Time to complete first unit = 112 hours
Learning rate = 90 %
We will use Standard Learning curve table ( with time for first unit = 112 hours and Learning rate = 90%) to calculate total time required to complete first 8 units .
Accordingly , total time required to complete first 8 units = 736.26 hours
Therefore , Total time required to complete next 7 units
= Time to complete first 8 units – Time to complete first unit
= 736.26 hours – 112 hours
= 624.26 hours
TIME REQUIRED TO COMPLETE NEXT 7 UNITS = 624.26 HOURS
TIME REQUIRED TO COMPLETE NEXT 7 UNITS = 624.26 HOURS