The possible paths and their corresponding cumulative durations as follows : A-B

ID: 373262 • Letter: T

Question

The possible paths and their corresponding cumulative durations as follows :

A-B-D-E-F = 6 + 2 + 5 + 4 + 3 = 20 days

A-B-D-E-G = 6 +2+5+4+6 = 23 days

A-C-D-E-F = 6+5+5+4+3 = 23 days

A-C-D-E-G = 6+5+5+4+6 = 26 days

Since A-C-D-E-G has the longer duration , it forms the critical path.

It is to be noted that all activities on critical path have ZERO slack

Therefore, activities A, C ,D , E and G have ZERO slack

Slack of activity B = Duartion A-C-D - Duration A-B-D = 16 - 13 = 3

Slack for activity F

= Duration of A-C-D-E-G – Duration of A-C-D-E-F

= 26 – 23

= 3 days

ACTIVITY

SLACK

A

0

B

3

C

0

D

0

E

0

F

3

G

0

ACTIVITY

SLACK

A

0

B

3

C

0

D

0

E

0

F

3

G

0

Explanation / Answer

Calculate the slack for each activity? Enter as intergers.

(daydays)

Slack (Days)

Activity Activity Time

(daydays)

Immediate Predecessor(s A 6 --- B 2 A C 5 A D 5 B,C E 4 D F 3 E G 6 E