Gerald Glynn manages the Michaels Distribution Center. After careful examination
ID: 381404 • Letter: G
Question
Gerald Glynn manages the Michaels Distribution Center. After careful examination of his database information, he has determined the daily requirements for part-time loading dock personnel. The distribution center operates 7 days a week, and the daily part-time staffing requirements are Th Su Requirements 4 Find the minimum number of workers Glynn must hire. Prepare a workforce schedule for these individuals so that each will have 2 consecutive days off per week and all staffing requirements will be satisfied. Give preference to the S-Su pair in case of a tie. (Note: If there is a tie that cannot be broken by following the preference to the S-Su pair, choose the pair closest to the beginning of the considered week.) The minimum number of workers is 7 workers. (Enter your response as a whole number) Specify the workforce schedule for each employee by indicating the day offs (other days are considered to be work days.) Make sure to give preference to the S-Su pair in case of a tie. (Note: If there is a tie that cannot be broken by following the preference to the S-Su pair, choose the pair closest to the beginning of the considered week, with Monday being considered as the first day of the week.) Employec Days offExplanation / Answer
M Tu Wed Thu Fri Sat Sun
Requirement 4 3 7 3 6 4 2
Let's find two consecutive days where the total requirement is the lowest. Saturday+Sunday=6 and Sunday+Monday=6. Since there is a tie, we would give the first worker (Worker 1) Saturday and Sunday off.
M Tu Wed Thu Fri Sat Sun
Worker 1 X X
Net Requirement 3 2 6 2 5 4 2
Now Sun+Mon have the lowest total requirement, so we can give worker 2 off on Sunday and Monday
Worker 2 X X
Net Requirement 3 1 5 1 4 3 2
Now Mon+Tu have the lowest net requirement. So, Worker 3 can take Mon+Tu off
Worker 3 X X
Net Requirement 3 1 4 0 3 2 1
Now, Thu+Fri and Sat+Sun have the lowest net requirement. We will prefer Sat+Sun off for Worker 4
Worker 4 X X
Net Requirement 2 0 3 0 2 2 1
Now, Mon+Tu=2 and Thu+Fri=2 have the lowest net requirement. We will prefer Mon+Tu as they are in the start of the week.
Worker 5 X X
2 0 2 0 1 1 0
Again Sat+Sun is the lowest along with Thu+Fri. We will prefer Sat+Sun
Worker 6 X X
Net Requirement 1 0 1 0 0 1 0
Thu+Fri=0. So, Thu+Fri is given preference
Worker 7 X X
Net Requirement 0 0 0 0 0 0 0
Days Off
Worker Days Off
1 Saturday+Sunday
2 Sunday+Monday
3 Monday+Tuesday
4 Saturday+Sunday
5 Monday+Tuesday
6 Saturday+Sunday
7 Thursday+Friday