Calculate the direct cost of labor for the project team using the following data
ID: 424750 • Letter: C
Question
Calculate the direct cost of labor for the project team using the following data. What are the costs for the individual project team members? What is the overall direct cost of labor?
Your response should be at least 75 words in length.
Explanation / Answer
Ans. Total Direct Labor Cost = Hourly Rate * Hours Needed * Overhead Charge * Personal Time Rate
So, Jonathan Direct Labor Cost = 17*60*1.35*1.12 = 1542.24
Susan Direct Labor Cost = 31*120*1.8*1.12 = 7499.52
Debra Direct Labor Cost = 9*40*1.35 = 486
Bobby Direct Labor Cost = 34*65*1.8*1.13 = 4495.14
Total Direct Labor Cost = 14,022.9