Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Case Study 8.2 Boston’s Central Artery/Tunnel Project Since the “Big Dig” projec

ID: 431277 • Letter: C

Question

Case Study 8.2 Boston’s Central Artery/Tunnel Project Since the “Big Dig” project was first introduced in the previous edition of this textbook, a number of additional events have occurred that make it important for us to revisit the original story and update the current status of this monumental project. When it was opened in 1959, Boston’s Central Artery highway was hailed as a marvel of engineering and forward- thinking urban planning. Designed as an elevated six-lane highway through the middle of the city, the highway was intended to carry a traffic volume of 75,000 vehicles a day. Unfortunately, by the early 1980s, the Central Artery was burdened by a daily volume of more than 200,000 vehicles, a nearly threefold ­increase over the anticipated maximum traffic levels. The ­result was some of the worst urban ­congestion in the country, with traffic locked bumper to bumper for more than 10 hours each day. At over four times the national average, the accident rate for the Central Artery added to commuters’ misery. Clearly, the Central Artery—a crumbling, overused, and ­increasingly dangerous stretch of highway—had outlived its usefulness.

Michael Dwyer/Alamy

The solution to the problem was the advent of the Central Artery/Tunnel (CA/T) project, commonly known to people from the Boston area as the “Big Dig.” Under the supervision of the Massachusetts Turnpike Authority and using federal and state funding, the CA/T project comprises two main elements: (1) replacing the aging elevated roadway with an 8- to 10-lane underground expressway directly beneath the existing road, with a 14-lane, two-bridge crossing of the Charles River, and (2) extending Interstate 90 through a tunnel beneath South Boston and the harbor to Logan Airport. Originally conceived and initiated in the early 1980s, the project was a continuous activity (some would say “headache”) in the city for more than 20 years.

The technical challenges in the Big Dig were enormous. Employing at its peak about 5,000 workers, the project included the construction of eight miles of highway, 161 lane miles in all, almost half below ground. It required the excavation of 16 million cubic yards of soil, enough to fill the New England Patriots’ football stadium 16 times, and used 3.8 million cubic yards of concrete. The second major challenge was to perform these activities without disrupting existing traffic patterns or having a deleterious effect on the current highway system and its traffic flows. Thus, while miles of tunnels were being excavated underneath the old Central Artery, traffic volume could not be slowed on the elevated highway.

The project had been a source of controversy for several years, most notably due to its soaring costs and constantly revised budget. At the time of the project’s kickoff in 1983, the original projections for the project’s scope assumed a completion date of 1998 and one-time funding from the federal government to cover 60% of the project’s original $2.5 billion budget. In fact, the budget and schedule have been revised upward nearly constantly since the project kicked off. Consider the following budget levels:

Final cost projections soared to over $14.5 billion and the project officially wrapped up in late 2004, or seven years late. Cost estimates and subsequent expenditures were so bad that by 2000, a federal audit of the project concluded that the Big Dig was officially bankrupt. One component of the federal audit concluded that a major cause for runaway project costs was due to poor project management oversight. Specifically, it was found that project management routinely failed to hold contractors to their bids or to penalize them for mistakes, resulting in huge cost increases for the Big Dig. Because of the intense public scrutiny and sensitive nature of the project, managers also stopped tracking or publicly acknowledging escalating costs, fearing that the political backlash could cripple the project. In fact, Taxpayers for Common Sense, a nonpartisan watchdog group, charged that the project’s economics became so bad that managers delayed budgeting for contracts worth $260 million to a consulting firm because they could not offset such a large cost in the short term. In response to public outcry over the delays and rising costs, the project manager submitted his resignation.

Not surprisingly, the citizens of Boston have viewed the opening of the Big Dig with a genuine sense of ambivalence. Though a technological marvel that will undoubtedly improve the lives of its users, while reducing carbon monoxide emissions and improving the “green” reputation of the city, the project proved to be such a financial morass that public officials quietly canceled a planned celebration of a major section’s opening. Finger pointing and a search for the causes of the Big Dig’s poor cost estimation and control were vigorous. For its part, the Massachusetts Turnpike Authority planned a $150 million lawsuit against the firms that managed the project, arguing that many of the cost overruns could be attributed to poor project management and oversight.

Increasingly, the question being asked was: Were original cost estimates for the CA/T given in good faith or were they “tuned” to meet political realities? That is, did officials deliberately underestimate true project costs, fearing that the project would not have been approved in the beginning if the public was aware of its likely cost and scope? If so, the result has been to leave a sour taste in the mouths of the taxpaying public, convinced that the CA/T project represents a combination of brilliant technical achievement coupled with poor estimation and lax control. Former Massachusetts House Speaker Thomas Finnerman put the matter directly: “You’d be much, much better off saying upfront, factually, ‘Hey, it’s going to take umpteen years likely and umpteen billions dollars,’ rather than selling it as a kind of smoke and mirrors thing about, ‘Oh, it’s two billion and a couple of years’ work.’”

Aftermath: Reconsidering the Big Dig

Since the completion of the Big Dig, you would expect the commotion to have died down, the complaints to have been resolved, and the people of Boston to have become used to the advantages of this enormous project. Unfortunately, that has not been the case. Since its “completion” in early 2004, bad press, disasters, and accountability continue to dog the Central Tunnel/Artery system.

In 2001, prior to the completion of the project, thousands of leaks began appearing in the ceiling of sections of the tunnel system. The cause? Records suggest that the primary contractor for the concrete pouring, Modern Continental, failed to remove debris prior to pouring concrete, resulting in flaws, cavities, and pockets of weakness in the ceiling and walls of the tunnels. In May 2006, six employees of the main supplier of concrete were arrested for falsifying records.

In fact, 2006 was a very bad year for the Big Dig for a variety of reasons. On July 10, 2006, the bolt and epoxy system holding four sections (12 tons) of concrete ceiling panels failed, causing a section to collapse onto the tunnel roadway and kill a passenger in a car passing beneath the section at the time. That month, a detailed inspection of the ceiling panels throughout the tunnel system identified an additional 242 bolts that were already showing signs of stress! The tunnel system was shut down for the month of August for inspection and repairs. Also in August, the state assumed control of the Central Tunnel/Artery from the Turnpike Authority, citing the TA’s poor record of supervision and effective project control.

The tragedy became something close a to farce when the Turnpike Authority and Federal Highway Administration refused to release critical documents to the state, including:

Deficiency reports flagging initial substandard work

Construction change orders and contract revisions

Inspection reports on workmanship and building material quality

Until the court system orders the release of all project documents, we may never know the extent of mismanagement and poor decision making that dogged the development of the CT/A. From a public relations perspective, however, the fighting between state and federal authorities over oversight and control of the troubled project is a continuing black eye for all parties involved.

In early 2008, the contractors for the Big Dig, including primary contractors Bechtel and Parson Brinckerhoff, were ordered to pay $450 million to settle the state’s lawsuit over the 2006 tunnel collapse. Though this settlement does not absolve the contractors from future lawsuits, it does settle some of the more egregious failures that occurred while they led the project. Michael Sullivan, the U.S. Attorney who led the lawsuit, noted that the contractors originally made a profit of about $150 million from the Big Dig; however, “They lost money as a result of the failures that occurred under their watch.”26

QuestionsEach essay should begin with an paragraph that introduces the topic of your essay and what will be conveyed.  Several paragraphs should follow that incorporate responses to the leading questions as well  as your individual analysis, examples, and conclusions. APA FORMAT!!!!!!!!!!!!!!ANSWER ALL QUESTION PLEASE THANK YOU!!!!!!!!! AGAIN IN APA FORMAT

Consider the following statement: “Government-funded projects intended to serve as ‘prestige projects,’ such as the ‘Big Dig,’ should not be judged on the basis of cost.” Do you agree or disagree with this statement? Why?

Project success is defined as adherence to budget, schedule, functionality (performance), and client satisfaction. Under these criteria, cite evidence that suggests the “Big Dig” project was a success and/or failure.

What are the lessons to be learned from the “Big Dig” project? Was this a failure of project estimation or project control by the contractors and local government?

Year Budget (in billions) 1983 ?2.56 1989 ?4.44 1992 ?6.44 1996 10.84 2000 14.08 2003 14.63

Explanation / Answer

1. Consider the following statement: “Government funded projects intended to serve as “prestige projects” such as the “Big Dig” should not be judged on the basis of cost”. Do you agree or disagree with this statement? Why?

            I would have to disagree with the idea that a project shouldn’t be judged based on the cost. This would go for any project regardless if it is a prestige project and regardless of who is paying for it. In my opinion, cost plays an important role in every project and whoever is paying for the project should be concerned about the costs of the project. Especially considering a government-funded project is using taxpayer dollars to fund a project and if the cost keeps going up then the citizens would be forced to pay more and in the end, the benefit won’t outweigh the costs in the eyes of the citizens.

2. Project success is defined as adherence to budget, schedule, functionality (performance), and client satisfaction. Under these criteria, cite evidence that suggests the “Big Dig” project was a success and/or failure.

            Based on these factors I would say there was plenty of evidence to show that the project was a failure. As noted in the text the original completion date was targeted for 1998 and it didn’t finish until early in 2004. During the whole project, it was clear that the contractors were not meeting their expectations or meeting the schedules. The budget was originally projected to be at 2.56 billion and then by the time 2003 came around it was up to 14.63 billion dollars.

3. What are the lessons to be learned from the “Big Dig” project? Was that a failure of project estimation or project control by the contractors and local government?

           

            Some of the lessons to be learned from this project are that when you are dealing with such a large project there are many potentials for gaps. Additionally, there is room for error or even fraud since contractors could be submitting invalid bids just to appease the politicians. I personally feel like that there were failures in the project estimation and project control. The estimates kept changing because there was no control over the bids and holding the people submitting these accountable. The project management team and or local government should have been holding the contractors accountable ensuring that they were meeting the specifications they agreed to not exceeding the budget they submitted.

I REQUEST YOU TO KINDLY RATE THE ANSWER AS THUMBS UP. THANKS A LOT.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote