sim.edu.sg/d2/le/content/1498 Apple SMI.CONNECT DL pYahoo Sarublopup OCIC Bank 49875/viewContent/207376/View?ous 149875 SIM CONNECT D2L perations Management 2018 Quarter 3 (Jul-Sep) (L01 R) ? ? ? gown Us Course Home Content AssessmentsCommunication ePortfolio CA Submissions CAD02 CAD02 00 oWEN SUTANTO: Attempt 1 Chiziatopher's Cranks uses a machine that can produce 100 cranks per hour. The in operates 12 hours per day Ese days per week. Due to zeqularly seheduled peeventave saintessnce, the fsem expects the machine to be ronning during approximately 958 of the avaslable timo Based on experience with other prodcts the im expects to achieve an eftcenicy evel for the eranks of 85What the expected weekly outpot of crankso this conpany 1 ) 2) 3) 4) e 12 Saved PrtScn Home End N0

Explanation / Answer

Available working hours in a week = 12*5 = 60 hours

Working hours available excluding Preventive maintenance = 60*95% = 57

Net Working hours available basis efficiency level of 85% = 57*85% = 48.45 hours

Production per hour = 100

So, total production in a week = Production per hour*Working hours available = 100*48.45 = 4845 cranks