What is the maximum number of resource type X that would be required to complete

ID: 449559 • Letter: W

Question

What is the maximum number of resource type X that would be required to complete all activities at their earliest opportunities?

Project C comprises the following activities, all activities are finish-to-start. There are sufficient of resource type Y to complete their activities as required but only 3 employees of resource type X. In order to resolve any resource overloads within the stated capacity activity A is to be undertaken after activity D e activity E is to be undertaken after activity A. Assume that the project starts at time zero Activity Dependent Duration ResourceResource Code Days Person Days Type Upon None None 10 18 12 16 C and D F and G

Explanation / Answer

The maximum number of resources of type X required = 9+8+18+6= 41

Time calculations of earliest event time has no considertions here ( Time based has no effect on resource calculation here)