Question

Online University Portal X Bb 201620 Sp X M Chapt 12 ter operations Management x O Chase online C ezto.mheducation.com /hm.tpx Problem 12-9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 59 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Lead Time Item (weeks) On Hand Components 15 A(2), B (1), C(4) Saw 10 E (3), D 5 D (2), F(3) 65 E(2), D(2) 20 10 30 b. Develop the material requirements plan for component E using lot-for-lot ordering. (Leave no cells blank be certain to enter "0" wherever required.) em: E (3) & E (2) LT 1 wk Beg. Inv 3 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release HE Search the web and Windows 8:08 PM 5/11/2016

Explanation / Answer

Projected On Hand Calculation = Last Period Closing + Scheduled Receipt + Planned Receipt - Gross Requirement Net Requirement = Last Period Closing + Scheduled Receipt - Gross Requirement (If the above calculation results in negative amount, then such amount is taken as Net Requirement, else 0) Planned Receipt = If Net Requirement > 0, Planned Receipt as per Lot Size Planned Order Release = If Planned Receipt >0, Order as per Lead Time to be placed Item = Saw L4L SS = 0 LT : 2 Period 0 1 2 3 4 5 6 7 8 Gross Requirement 0 0 0 0 0 0 0 59 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 15 15 15 15 15 15 15 15 0 Net Requirements 0 0 0 0 0 0 0 44 Planned Receipts 0 0 0 0 0 0 0 44 Planned Order Release 0 0 0 0 0 44 0 0 2 units of A per saw are required when order for Saw is released. Item = A L4L SS = 0 LT : 1 Period 0 1 2 3 4 5 6 7 8 Gross Requirement 0 0 0 0 0 88 0 0 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 10 10 10 10 10 10 0 0 0 Net Requirements 0 0 0 0 0 78 0 0 Planned Receipts 0 0 0 0 0 78 0 0 Planned Order Release 0 0 0 0 78 0 0 0 2 units of C per saw are required when order for Saw is released. Item = C L4L SS = 0 LT : 2 Period 0 1 2 3 4 5 6 7 8 Gross Requirement 0 0 0 0 0 176 0 0 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 65 65 65 65 65 65 0 0 0 Net Requirements 0 0 0 0 0 111 0 0 Planned Receipts 0 0 0 0 0 111 0 0 Planned Order Release 0 0 0 111 0 0 0 0 3 Units of E is required when order for A is released. 2 Units of E are required when order for C is released. Item = E L4L SS = 0 LT : 1 Period 0 1 2 3 4 5 6 7 8 Gross Requirement 0 0 0 222 234 0 0 0 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 10 10 10 10 0 0 0 0 0 Net Requirements 0 0 0 212 234 0 0 0 Planned Receipts 0 0 0 212 234 0 0 0 Planned Order Release 0 0 212 234 0 0 0 0