36) A company has decided to implement DBR for a product line. The current lead
ID: 471034 • Letter: 3
Question
36)
A company has decided to implement DBR for a product line. The current lead time between the first
operation and the constraining operation is 10 days. What should the initial buffer size using DBR be
a)
10 days
b)
5 days
c)
5 hrs
d)
7 days
e)
None of the above
37)
A requirements-based system derives orders from:
A.
Customer requests
B.
Forecast
C.
Bill of materials
D.
Master schedule
38)
A replenishment-based system derives orders from:
A.
Capacity available
B.
Forecast or customer request
C.
Bill of materials
D.
Master schedule
Week Demand
1 20
2 60
3 30
4 20
39)
The parts explosion results in the following outputs:
A.
Purchase orders and S&OP (aggregate planning)
B.
Purchase orders and bill of materials
C.
Purchase orders and shop orders
D.
Shop orders and inventory orders
40)
According to TOC, when a constraint is internal we should evaluate product mix decisions based on:
a)
The product with the highest profit margin
b)
The product with the lowest unit cost
c)
The product with least activity-based allocations
d)
The throughput generated per unit time on the constraint (T/Cu)
e)
Marketing considerations
36)
A company has decided to implement DBR for a product line. The current lead time between the first operation and the constraining operation is 10 days. What should the initial buffer size using DBR be 10 days 5 days 5 hrs 7 days None of the above A requirements-based system derives orders from: Customer requests Forecast Bill of materials Master schedule A replenishment-based system derives orders from: Capacity available Forecast or customer request Bill of materials Master schedule Week Demand 20 60 30 20 40 The parts explosion results in the following outputs: Purchase orders and S&OP; (aggregate planning) Purchase orders and bill of materials Purchase orders and shop orders Shop orders and inventory orders According to TOC, when a constraint is internal we should evaluate product mix decisions based on: The product with the highest profit margin The product with the lowest unit cost The product with least activity-based allocations The throughput generated per unit time on the constraint (T/Cu)Explanation / Answer
Q36:ans=5 days(B)
q37:ans=Master schedule(D)
Q38:ans=Forecast or customer request(B)
q39:ans=Purchase orders and shop orders(C)
Q40:ans=(D)The throughput generated per unit time on the constraint (T/Cu)