Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

36) A company has decided to implement DBR for a product line. The current lead

ID: 471034 • Letter: 3

Question

36)

A company has decided to implement DBR for a product line. The current lead time between the first

operation and the constraining operation is 10 days. What should the initial buffer size using DBR be

a)

10 days

b)

5 days

c)

5 hrs

d)

7 days

e)

None of the above

37)

A requirements-based system derives orders from:

A.

Customer requests

B.

Forecast

C.

Bill of materials

D.

Master schedule

38)

A replenishment-based system derives orders from:

A.

Capacity available

B.

Forecast or customer request

C.

Bill of materials

D.

Master schedule


    Week               Demand

1                                       20

2                                       60
3                                     30

4                                      20




39)

The parts explosion results in the following outputs:

A.

Purchase orders and S&OP (aggregate planning)

B.

Purchase orders and bill of materials

C.

Purchase orders and shop orders

D.

Shop orders and inventory orders

40)

According to TOC, when a constraint is internal we should evaluate product mix decisions based on:

a)

The product with the highest profit margin

b)

The product with the lowest unit cost

c)

The product with least activity-based allocations

d)

The throughput generated per unit time on the constraint (T/Cu)

e)

Marketing considerations

36)

A company has decided to implement DBR for a product line. The current lead time between the first operation and the constraining operation is 10 days. What should the initial buffer size using DBR be 10 days 5 days 5 hrs 7 days None of the above A requirements-based system derives orders from: Customer requests Forecast Bill of materials Master schedule A replenishment-based system derives orders from: Capacity available Forecast or customer request Bill of materials Master schedule Week Demand 20 60 30 20 40 The parts explosion results in the following outputs: Purchase orders and S&OP; (aggregate planning) Purchase orders and bill of materials Purchase orders and shop orders Shop orders and inventory orders According to TOC, when a constraint is internal we should evaluate product mix decisions based on: The product with the highest profit margin The product with the lowest unit cost The product with least activity-based allocations The throughput generated per unit time on the constraint (T/Cu)

Explanation / Answer

Q36:ans=5 days(B)

q37:ans=Master schedule(D)

Q38:ans=Forecast or customer request(B)

q39:ans=Purchase orders and shop orders(C)

Q40:ans=(D)The throughput generated per unit time on the constraint (T/Cu)