The auto repair shop of Quality Motor Company uses standards to control the labo
ID: 2558077 • Letter: T
Question
The auto repair shop of Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below:
The record showing the time spent in the shop last week on motor tune-ups has been misplaced. However, the shop supervisor recalls that 230 tune-ups were completed during the week, and the controller recalls the following variance data relating to tune-ups:
Required:
1. Determine the number of actual labor-hours spent on tune-ups during the week.
2. Determine the actual hourly rate of pay for tune-ups last week. (Round your answer to 2 decimal places.)
Standard Hours Standard Rate Standard Cost Motor tune-up 1.50 $6.20 $9.30Explanation / Answer
Labour efficiency variance = 408F+615U = 1023 U
Labour efficiency variance = (standard hour-actual hour)Standard rate
-1023 = (230*1.5-X)6.20
-1023 = 2139-6.20X
6.20X = 3162
X(actual hour) = 510 hour
Labour rate variance = (Standard rate-actual rate)actual hour
408 = (6.20-X)510
408 = 3162-510X
510X = 2754
X(actual rate) = 5.4 per hour