Calculate the NPV of each project. Calculate the IRR of each project. Botany Des
ID: 2645553 • Letter: C
Question
Calculate the NPV of each project.
Calculate the IRR of each project.
Botany Designs is looking to revamp its manufacturing facility and has two different options they can choose from. The initial investment for each option is $100,000. They have set a minimum payback requirement of 4 years. The cost of capital is going to be 11% for each project.
Cash Inflows for years 1-5 are:
Year
Project Speedy (S)
Project Quality (Q)
1
32000
22500
2
32000
22500
3
32000
22500
4
32000
22500
5
32000
22500
Year
Project Speedy (S)
Project Quality (Q)
1
32000
22500
2
32000
22500
3
32000
22500
4
32000
22500
5
32000
22500
Explanation / Answer
NPV ( Project Speedy ) =100000- PV of annuity(A=32000,I=11% , N=5)=3.6959*32000-100000=18268.8
NPV((Project Quality)=100000- PV of annuity(A=22500,I=11% , N=5)=3.6959*22500-100000=-16842.3
Cell Speedy Quality A1 -100000 -100000 A2 32000 22500 A3 32000 22500 A4 32000 22500 A5 32000 22500 A6 32000 22500 By excel,IRR(A1:A6,0.01) 18% 4%Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.