A project will cost $4,819,724 and its expected to earn zero after one year, but
ID: 2648112 • Letter: A
Question
A project will cost $4,819,724 and its expected to earn zero after one year, but $3,009,913 at the end of the second year, and $2,779, 333 at the end of the third year. Your company currently has borrowing worth $73,789,532 for which the company is paying 7.4% per year interest, and the owners of the company have invested a total of $149,815,110.40; and they generally want a return of 15% per year. Corporate tax rate is at 37%. Is this a good project or not? How many percent return/loss will your company have if you go ahead with the project?
Explanation / Answer
Evaluation of Project Year 0 Year 1 Year 2 Year 3 Initial cost $ (4,819,724.00) Expected earnings (Net of tax) $ - $ 1,896,245.19 $ 1,750,979.79 3009913*(1-0.37) 2779333*(1-0.37) Less : Interest cost (Net of tax) $ (227,731.96) $ (227,731.96) $ (227,731.96) 4819724*7.5%*(1-0.37) Net cash flows after tax (CFAT) $ (4,819,724.00) $ (227,731.96) $ 1,668,513.23 $ 1,523,247.83 PVF (15%) 1.00000 0.86957 0.75614 0.65752 PV = CFAT *PVF $ (4,819,724.00) $ (198,027.79) $ 1,261,635.71 $ 1,001,560.17 NPV = Sum of PVs $ (2,754,555.90) we can see that the NPV of the project in negative, hence this project should not be accepted IRR of the project -28% using formula =IRR() IF the Co. go ahead with the project the loss shall be 28% IRR is negative 28% that is 15+28 = 43 % Less that required rate 15%
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.