What is the present net value of a project with the following cash flows if the
ID: 2700320 • Letter: W
Question
What is the present net value of a project with the following cash flows if the discount rate is 17 percent?Year Cash Flow 0 -$59,200 1 21,600 2 28,300 3 14,400 4 7,200
A -$8,406.11 B -$7,231.71 C -$3,089.16 D $1,407.92 E $3,508.01 A -$8,406.11 B -$7,231.71 C -$3,089.16 D $1,407.92 E $3,508.01 What is the present net value of a project with the following cash flows if the discount rate is 17 percent?
Year Cash Flow 0 -$59,200 1 21,600 2 28,300 3 14,400 4 7,200
A -$8,406.11 B -$7,231.71 C -$3,089.16 D $1,407.92 E $3,508.01
Explanation / Answer
NPV = 21600/1.17 + 28300/(1.17^2) + 14400/(1.17^3) + 7200/(1.17^4) - 59200 = -$7231.71
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.