QUESTION 16
In capital budgeting analysis, the riskiness of a project is evaluated to:
determine the multiple internal rates of return from the project.
determine the appropriate rate of return to use for computing the present value of the estimated cash flows.
determine the duration of the project.
determine the role of management to ensure project completion within stipulated time
A.determine the multiple internal rates of return from the project.
B.determine the appropriate rate of return to use for computing the present value of the estimated cash flows.
C.determine the duration of the project.
determine the role of management to ensure project completion within stipulated time
Explanation / Answer
In capital budgeting analysis, the riskiness of a project is evaluated to: determine the appropriate rate of return to use for computing the present value of the estimated cash flows
It tells us whether we will achieve the positive cash flows from the project or not.