Consider a process with four stations – Stations 2 & 3 have identical operations
ID: 3394617 • Letter: C
Question
Consider a process with four stations – Stations 2 & 3 have identical operations, so any part after fabrication can go to either Station 2 or Station 3 based on availability. The following table shows the unit processing times:
Station 1
2 min/part
Station 2
3 min/part
Station 3
3 min/part
Station 4
1 min/part
Question 1) Which station is the bottleneck?
Question 2) If the throughput rate (demand rate) is 20 units/hr, what is the utilization of Station 2?
Please solve in excel if you can, please show work. Thank you
Station 1
2 min/part
Station 2
3 min/part
Station 3
3 min/part
Station 4
1 min/part
Assembly Station 2 Fabrication Station 1 Testing Station 4 Assembly Station 3Explanation / Answer
1. Station 1 is the bottleneck.
Explanation: While the time taken by stations 2 and 3 is more, their work is divided, hence the average time taken = 1.5 min.
2. Net demand = 20 units/hour
As work is divided between 2 and 3, demand from 2 = 10 units/hour
Capacity of 2 = 20 units/hour(60/3)
Utilization = 10/20 = 0.5