Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Expando, Inc., is considering the possibility of building an additional factory

ID: 361003 • Letter: E

Question

Expando, Inc., is considering the possibility of building an additional factory that would produce a new addition to their product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $6 million. If demand for new products is low, the company expects to receive $11 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects $12 million in discounted revenues using the small facility. The second option is to build a large factory at a cost of $11 million. Were demand to be low, the company would expect $12 million in discounted revenues with the large plant. If demand is high, the company estimates that the discounted revenues would be $16 million. In either case, the probability of demand being high is 0.40, and the probability of it being low is 0.60. Not constructing a new factory would result in no additional revenue being generated because the current factories cannot produce these new products. a. Calculate the NPV for the following: (Leave no cells blank - be certain to enter "0" wherever required. Enter your answers in millions rounded to 1 decimal place.) Plans NPV Small facility $ million Do nothing million Large facility million

Explanation / Answer

Net present value of any option

= Discounted revenue adjusted for probabilities under low and high demand – Cost to build

= ( Probability of high demand x Discounted revenue under high demand + Probability of low demand x Discounted revenue under low demand ) – Cost to build

= ( 0.4 x Discounted revenue under high demand + 0.6 x Discounted revenue under high demand ) – Cost to build

Therefore,

NPV of the small facility , $ million

= ( 0.4 x 12 + 0.6 x 11 ) - 6

= 4.8 + 6.6 - 6

=11.4 - 6

= 5.4

Similarly , NPV for the large facility

= ( 0.4 x 16 + 0.6 x 12 ) – 11

= 6.4 + 7.2 - 11

= 13.6 - 11

= 2.6

Not constructing any factory would not have any revenue as well as cost items. Hence , its NPV will be Zero

PLAN

NPV

Small facility

5.4

Million

Do nothing

0

Million

Large facility

2.6

Million

PLAN

NPV

Small facility

5.4

Million

Do nothing

0

Million

Large facility

2.6

Million

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote