Consider a process consisting of three resources. Assume there exists unlimited

ID: 383462 • Letter: C

Question

Consider a process consisting of three resources. Assume there exists unlimited demand for the product. Resource 1 has a processing time of 4 minutes per unit. Resource 2 has a processing time of 10 minutes per unit. Resource 3 has a processing time of 9 minutes per unit. Resource 1 Resource 2 Resource 3 Answer is complete but not entirely correct. All three resources are staffed by one worker. The flow diagram is shown above. Round "Capacity of resource" to 3 decimal places and other numbers to whole numbers What is the capacity of resource 2? What is the bottleneck in the process? What is the utilization of resource 27 0.100 units per 2 Resource 100percent 1,820 minutes a. minute b. c. How long does it take the process to produce 182 units starting with an empty system, assuming this is a worker-paced process? d.

Explanation / Answer

Total time taken by all resources is 23 minutes for each product

Therefore the time taken by 182 products is 4186 minutes (182×23)

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote