Consider a process consisting of three resources. Assume there exists unlimited

ID: 386864 • Letter: C

Question

Consider a process consisting of three resources. Assume there exists unlimited demand for the product.

Resource 1 has a processing time of 5 minutes per unit

Resource 2 has a processing time of 2 minutes per unit.

Resource 3 has a processing time of 5 minutes per unit.

All three resources are staffed by one worker and each worker gets paid $ 11 per hour. Use two decimals where applicable.

a. What is the cost of direct labor? $ dollars per unit

b. What is the labor content? minutes per unit

c. How much idle time does the worker at resource 3 have per unit? minutes per unit

d. What is the average labor utilization? percent

e. Assuming the demand rate is 24 units per hour, what is the takt time? minutes per unit

f. Assuming the demand rate is 24 units per hour, what is the target manpower?

Explanation / Answer

Resource 1 : 5 minutes/ unit

Resource 2 : 2 minutes / unit

Resource 3 : 5 minutes / unit

Resource 1 and resource 3 are the bottlenecks since they have maximum processing time per unit which also decides capacity of the process.

Therefore, capacity of the process is 5 minutes/ unit

Hence hourly capacity of the process = 60 / 5 = 12 units/ hour

There are 3 workers at 3 resources each of whom is paid $11 per hour . Therefore , total hourly wages paid = $11 x 3 = $33

Therefore , cost of direct labour = $33 / 12 = $2.75 / unit

Cost of direct labour = $2.75 / unit

= Process capacity in terms of minutes/ unit – Capacity of resource 3 in terms of minutes/ unit

= 5 minutes/ unit – 5 minutes/ unit

= 0

Idle time the worker has at resource 3 per unit = 0 minutes

= Total labour content in minutes/ unit / ( Number of resources x Process capacity in minutes / unit ) x 100

= 12 / ( 3 x 5 ) x 100

= ( 12/15) x 100

= 80%

=60 minutes/ 24 units

= 2.5 minutes/ unit

This will be possible by :

Deploying 2 workers at resource 1 which will make effective processing time = 5 minutes/ 2 workers = 2.5 minutes/ worker

Deploying 2 workers at resource 3 which will make effective processing time = 5 minutes/ 2 workers = 2.5 minutes / worker

There is no need of deploying additional manpower at resource 2 since its processing time of 2 minutes/ unit is already less than takt time of 2.5 minutes/ unit

Therefore target manpower

= 2 ( resource 1 ) + 1 ( resource 2 ) + 2 ( resource 3 )

= 5

Target manpower = 5

Cost of direct labour = $2.75 / unit