Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

act./ immed.pred/ NT/ CT/ NC / CC a ---- 12 / 8 / 8,000/ 12,000 b ----- 14 / 10/

ID: 403226 • Letter: A

Question

act./ immed.pred/ NT/ CT/ NC / CC a ---- 12 / 8 / 8,000/ 12,000 b ----- 14 / 10/ 5,000/ 7,500 c ----- 8 / 8 / 10,000/ 10,000 d A 5 / 3 / 6,000/ 8,000 e A 4 / 3 / 5,000/ 7,000 f B,C,E 6 / 5 / 9,000/ 12,000 g C 10 / 8 / 5,000/ 8,000 1) construct activities node chart(use just the normal task times) 2)what activities are on the critical path? & what is the time? 3)construct a lp formulation( include obj function & all constraints) that reduce project completion time by 2 weeks 4)solve using excel solver

Explanation / Answer

Ans:- dear i am best in operation management .

but i'm not able to understand the data you provided .plz repost it in right manner .

I'm pretty sure i'll do that .