Given the following manufacturing precedence relationships, compute the cycle ti

ID: 442640 • Letter: G

Question

Given the following manufacturing precedence relationships, compute the cycle time per day and the minimum number of workstations assuming eight working hours a day and 400 products need to be produced per day.

TASK DESCRIPTION       TASK TIME        PRECEDING TASK

A            Punching              30 seconds

B            Bending               20 seconds          A

C            Combining           30 seconds          B

D            Painting               40 seconds          C

E             Polishing              60 seconds          D

                                             --------------

                                             180 seconds

Explanation / Answer

Cycle time per day=Total Production time available/Desired unit of output

Cycle time per day=8*60*60sec/400=72sec

Minimum number of workstation required=Total Task time/Cycle time

Minimum number of workstation required=180/72=2.5

Since we can’t have half workstation, Minimum workstation required=3