Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider a budget allocation problem where $30 million is available for a number

ID: 457042 • Letter: C

Question

Consider a budget allocation problem where $30 million is available for a number of projects listed below. The investment required in each project along with the expected return in terms of utility is also given. (a) The problem is to find which projects should be financed in order to maximize the total expected utility not exceeding the budget limitation. Formulate the problem in integer programming. (b) Now suppose there are additional conditions in selecting the projects. Write the constraints for these conditions. Any two of the first four projects must be undertaken. Projects 1 and 3 must be taken simultaneously or not taken at all. Project-1 will be undertaken only if project-3 is undertaken but project-3 is not conditional on project-1 (that means, you can have project-3 without project-1, but you cannot have project-1 unless project-3 is undertaken).

Explanation / Answer

a)

Project   1

Project 2

Project 3

Project 4

Project 5

Decision Var.

X1

X2

X3

X4

X5

Changing Cells

1

0

1

1

1

Budget ($ Millions)

6

18

10

9

4

Expected Utility

18

16

12

25

14

Constraints

Cost

29

<=

30

Constraint 2 (Binary)

1

=

Bin

Constraint 3 (Binary)

0

=

Bin

Constraint 4 (Binary)

1

=

Bin

Constraint 5 (Binary)

1

=

Bin

Constraint 6 (Binary)

1

=

Bin

Obj. Function

69

b)

1) Any two of the first four projects must be undertaken

                Constraint   X1 + X2 + X3 + X4 = 2

2) Project 1 and 3 must be taken simultaneously or not taken at all

              Constraint   X1 + X3 = 2 &

                                   X1 + X3 = 0        

3) Project 1 will be taken only if Project 3 is undertaken

                Constraint   X3 = 1 &

                                     X1 + X3 = 2

4) Project 3 is not conditional on Project 1

                Constraint X3 =1 &

                                X1 + X3 =1 (or)

                                X1 + X3 =2

Project   1

Project 2

Project 3

Project 4

Project 5

Decision Var.

X1

X2

X3

X4

X5

Changing Cells

1

0

1

1

1

Budget ($ Millions)

6

18

10

9

4

Expected Utility

18

16

12

25

14

Constraints

Cost

29

<=

30

Constraint 2 (Binary)

1

=

Bin

Constraint 3 (Binary)

0

=

Bin

Constraint 4 (Binary)

1

=

Bin

Constraint 5 (Binary)

1

=

Bin

Constraint 6 (Binary)

1

=

Bin

Obj. Function

69

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote