Construction project managment :

QUESTION 1

Changes may be authorized through verbal communications.

True

False

10 points   

QUESTION 2

Most time extension requests are fairly subjective, as the true impact of the change is rarely clearly determined.

True

False

10 points   

QUESTION 3

The architect or owner representative causes the contractor to perform work outside the contract in a ____.

owner-directed change

constructive change

jobsite discovery change

substitution change

10 points   

QUESTION 4

AIA  Document A201 requires that the claim be made within ____ after recognizing the change

5 days

7 days

14 days

21 days

10 points   

QUESTION 5

A(n) [   ] is an unresolved change request

Explanation / Answer

Hi,

PLZ GIVE THUMBS UP.

A1 ] The changes made due to verbal communications are valid.So it is true.

A 2]  Whenever the true impact of the change is rarely clearly determined in such cases time extension requests are done.So it is true.

A3] The architect or owner representative causes the contractor to perform work outside the contract in a Constructive change where construction documents error and omissions fall in this category.

A 4] AIA  Document A201 requires that the claim be made within 21 days after recognizing the change