Construction project managment :
QUESTION 1
Changes may be authorized through verbal communications.
True
False
10 points
QUESTION 2
Most time extension requests are fairly subjective, as the true impact of the change is rarely clearly determined.
True
False
10 points
QUESTION 3
The architect or owner representative causes the contractor to perform work outside the contract in a ____.
owner-directed change
constructive change
jobsite discovery change
substitution change
10 points
QUESTION 4
AIA Document A201 requires that the claim be made within ____ after recognizing the change
5 days
7 days
14 days
21 days
10 points
QUESTION 5
A(n) [ ] is an unresolved change request
Explanation / Answer
Hi,
PLZ GIVE THUMBS UP.
A1 ] The changes made due to verbal communications are valid.So it is true.
A 2] Whenever the true impact of the change is rarely clearly determined in such cases time extension requests are done.So it is true.
A3] The architect or owner representative causes the contractor to perform work outside the contract in a Constructive change where construction documents error and omissions fall in this category.
A 4] AIA Document A201 requires that the claim be made within 21 days after recognizing the change