Construction project managment:

QUESTION 11:

It should be noted that change may be authorized through verbal communications.

True

False

QUESTION 12:

The fee for overhead and profit allowed in change orders is not stated in the Contract Documents.

True

False

QUESTION 13:

During project closeout, follow-up with subcontractors and suppliers usually is necessary.

True

False

QUESTION 14:

The objective in financial resolution is to resolve all outstanding cost commitments, establish a final project cost, and determine profit or loss.

True

False

QUESTION 15:

The primary purpose of the ____ is to achieve the goals of the project.

analysts

subcontractors

construction crew

management team

Explanation / Answer

QUESTION 11

FALSE

QUESTION 12

FALSE

QUESTION 13

TRUE

QUESTION 14

TRUE

QUESTION 15

ANSWER IS MANAGEMENT TEAM