Construction project managment: QUESTION 11: It should be noted that change may
ID: 1711054 • Letter: C
Question
Construction project managment:
QUESTION 11:
It should be noted that change may be authorized through verbal communications.
True
False
QUESTION 12:
The fee for overhead and profit allowed in change orders is not stated in the Contract Documents.
True
False
QUESTION 13:
During project closeout, follow-up with subcontractors and suppliers usually is necessary.
True
False
QUESTION 14:
The objective in financial resolution is to resolve all outstanding cost commitments, establish a final project cost, and determine profit or loss.
True
False
QUESTION 15:
The primary purpose of the ____ is to achieve the goals of the project.
analysts
subcontractors
construction crew
management team
Explanation / Answer
QUESTION 11
FALSE
QUESTION 12
FALSE
QUESTION 13
TRUE
QUESTION 14
TRUE
QUESTION 15
ANSWER IS MANAGEMENT TEAM