Construction project managment: QUESTION 21 The ____ is responsible for tool sec
ID: 1711056 • Letter: C
Question
Construction project managment:
QUESTION 21
The ____ is responsible for tool security.
subcontractor
foreman
apprentice
field engineer
QUESTION 22
The three primary elements of a construction project are cost, ____, and quality.
quantity
time
planning
identification
QUESTION 23
Overall, ____ accounts for the least percentage of construction waste.
rocks
gypsum board
metal
concrete
QUESTION 24
The number one existing building problem and insurance industry concern of the past 10 years has been ____.
wind damage
water damage
mold
frame instability
QUESTION 25
____ software allows a single server to host a software application and then allows multiple sites to access it.
Word processing
Application-serving
BIM
Database
Explanation / Answer
21 Foreman
22 Time(All these three elements are independent each other)
23 Gypsum board
24 Mold (Air quality issue accumulation of mold due to moisture trapped in the building)
25 Application-serving (Means multiple sites have a continuous access all at the same time)
Related Questions