Consider a process consisting of three resources. Assume there exists unlimited

ID: 2820017 • Letter: C

Question

Consider a process consisting of three resources. Assume there exists unlimited demand for the product Resource 1 has a processing time of 2 minutes per unit. Resource 2 has a processing time of 3 minutes per unit. Resource 3 has a processing time of 7 minutes per unit. Resource 1 Resource 2 Resource3 All three resources are staffed by one worker. The flow diagram is shown above Round 'Capacity of resource" to 3 decimal places and other numbers to whole numbers 0.333 units per minute 3 Resource percent a. What is the capacity of resource 2? b. What is the bottleneck in the process? c. What is the utilization of resource 2? d How long does it take the process to produce 205 units starting with an empty system, assuming this is a worker-paced process? 1.440 minutes

Explanation / Answer

Utilization of resource 2 = Flow rate/Capacity Flow rate - 1 minute utilization of resource 2 = 0.143/0.333 43% Flow rate is the same as process capacity which is equivalentto capacity of bottleneck Here the bottleneck is resource 3 Process capacity of resource 3 is 1/7 0.143

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote